We cut the four-meter-long scrap rollers, with a diameter of 60 to 70 centimeters, into short pieces with cutting torches, with a maximum weight of one tonne each. We used the crawler crane to lift them into containers so that we could remove them in a controlled and safe manner. We also removed all other materials from the hall in this way.
There was an overhead crane in the hall. We had it technically inspected and then used it for lifting and removing demolition waste. Convenient and efficient!
Because the scrap rolling mill was bankrupt, there was no external safety control. That is why we have made all the provisions and managed the risks ourselves. And with good results: no incidents and a completely safe implementation. The entire project took eight months to complete.
The Quality and Health, Safety and the Environment policy is an ongoing process. That is why DDM is continuously working on improving all these areas to keep improving safety levels.
DDM was rewarded with a World Demolition Award in the Civils category.
Removing 5 arch bridges over the Amsterdam Rhine Canal was an intensive job. The schedule was tight and the expectations of all employees were high. But with a joint effort and incredible passion, DDM has successfully removed and recycled the 5 bridges within schedule.
Every year DDM holds a number of safety days to boost safety awareness.
Last year's objectives are evaluated and new objectives are determined. All managers and all operational employees discuss safety, policy and vision together. In addition to all regular training courses, DDM offers workshops and training to all employees during these days to take the qualities of the professionals to an even higher level. Together with all DDM employees, we are working on an increasingly higher safety ethic. Everyone at DDM carries out their work in a safe and healthy manner, with sufficient attention to the environment. And they're getting better at it. This applies to everyone; back to work healthy and safe and back home healthy.
Dow has awarded DDM a certificate for Outstanding Safety Performance.
Following various demolition and disassembly projects that DDM carries out worldwide for Dow Chemical Company, DDM has received recognition for its excellent safety performance during implementation. DDM always continues to strive for a higher level of safety. Safety First! Read below a quote from the letter that DDM received from Dow. “In summary, DDM continues to deliver excellent performance in safely planning and executing all work related to Dow demolition projects. We truly believe that your company's exceptional efforts continue to be a reflection of the leadership and support of you and the entire DDM Management team. "