"THE PRODUCTION HAL WAS DELIVERED EMPTY AND READY FOR FUTURE USE"

Dismantling production lines for reuse

DISMANTLING Projects | Dismantling production lines

DEMOLITION Projects | Dismantling production lines

Our client, in the south of the Netherlands wanted to transfer their production facilities to another location. DDM was asked to disassemble the existing production lines for reuse in the new location.

The project had to be completed within a 6 week window. We put together a team of dismantling specialists along with creating a detailed project plan which was delivered to the team during a walk-through of the project.

We started dismantling the power supply. Once everything was disconnected, we started to meticulously disassemble the loose parts of the production and packaging lines. Subsequently, the steel structures belonging to the production lines that were no longer required were demolished including the concrete structures. Next to the production hall were a number of silos that were part of the production process. We dismantled the silos with mobile cranes and prepared them for onward transport. As soon as the disassembly work was finished, we demolished the complete steel construction. The production hall was completely cleared of all plant and equipment and handed over to the client ready for future use.

We have been able to work very well with the client. The high level of teamwork on the project has ensured that we have delivered the work within the set period of 6 weeks to the full satisfaction of the customer. The completion report was a huge boost to the project team with praise for the teams good work!!

DISMANTLING

DEMOLITION

Location

Born, the Netherlands

Objects

Elektrische installatie
Fabriek / Hal

Deployment

  • - 5 Dismantling Specialists
  • - Specialist Dismantling Tools
  • - Aerial Platforms
  • - Mobile Demolition Excavator
  • - Mobile Lifting Gantries
  • - Heavy Lift HIAB’s

Project duration

6 weeks

Safety First! Always.

The Quality and Health, Safety and the Environment policy is an ongoing process. That is why DDM is continuously working on improving all these areas to keep improving safety levels.