"THERE WAS ONLY ONE THING FOR IT: TAKE IT ALL APART!"

How do you fit a compounding unit in sea containers?

DISMANTLING Projects | Compounding unit

In Kuantan (Malaysia), DDM efficiently dismantled a compounding unit, placed it in sea containers and shipped it to Egypt. An unusual job!

The challenge in moving this installation was that the building and part of the steel structure had to remain intact, and there was nowhere to put heavy equipment. The compounding unit was placed in its entirety 7 years ago through the roof of the factory hall. However, removing the systems through the roof was no longer possible.

DDM had the solution: take the installation apart completely. Special equipment was using for dismantling the extruder, which was then moved using a roller system and placed in a sea container. All switching panels, cabling, the transformer and various large and small silos were also dismantled, packed and loaded.

DISMANTLING

Location

Kuantan, Malaysia

Deployment

  • - 4 dismantling specialists
  • - Forklift truck
  • - Hydraulic platforms
  • - 35t hydraulic lifting crane

Size

silos
extruder
transformer
electrical installation
part of the steel structure

Project duration

3 weeks

RELOCATION

CONSULTING AND ADVISE

TAGGING AND MARKING

PACKING

Safety First! Always.

The Quality and Health, Safety and the Environment policy is an ongoing process. That is why DDM is continuously working on improving all these areas to keep improving safety levels.
Find out more

PROJECT LOCATION

Services Latest DDM