Petrochemical plants in Hamburg

The project in Hamburg will soon be completed. This project started in the summer of 2016, and to date the DDM team has worked hard to complete the entire project.

Besides a number of different factories, DDM also removed columns, two 80-metre high chimneys, tanks, various different structures made of steel and reinforced concrete and more than 50 kilometres of piping from the premises. Generally speaking, this resulted in a scrap quantity of about 14,000 tons. The asbestos removal was carried out simultaneously in three asbestos containments. A team of about 25 specialised employees carried out these activities.