Relocating a PET plant from Germany to the Netherlands

"5,000 TONS OF EQUIPMENT RELOCATED"

Moving a PET factory from Germany to the Netherlands

RELOCATION Projects | PET factory

How do you move a PET factory from Germany to the Netherlands? With DDM

Dismantling specialists from DDM first meticulously mapped out the factory. They determined the ‘as-built’ situation by a combination of measuring and 3D scanning. After each part had been carefully labelled, everything was dismantled. With the exception of the concrete structures, each part was labelled, packaged and relocated. The other structures and the foundations, which were largely made of concrete, were demolished. The site in Germany was handed over, looking as if nothing had ever been there.

At the new location in Rotterdam, each component was put back in the right place. All the nuts and bolts were screwed in and the cables were reconnected. The collaboration with the client was perfect: the factory is running again as before.

RELOCATION

Locations

Offenbach am Main, Germany & Rotterdam Maasvlakte, the Netherlands

Deployment

  • - 120 specialisten
  • - Verschillende transportmethodes
  • - Meerdere (hydraulische) hijskranen 200-500T
  • - Transporttrailers
  • - 120 specialists
  • - Various transport methods
  • - Multiple hydraulic lifting cranes of 200-500t
  • - Transport trailers

Size

5000 Tons of equipment relocated

Project duration

12 months

RELOCATION

AS BUILD AND 3D SCANNING

TAGGING AND MARKING

PACKING

TRANSPORT

DISMANTLING

Safety First! Always.

The Quality and Health, Safety and the Environment policy is an ongoing process. That is why DDM is continuously working on improving all these areas to keep improving safety levels.