DISMANTLING Projects | Truck cab production line
After a long period of preparations, the truck factory in Ghent closed for one month according to schedule. In that time, DDM dismantled the complete cab production line and rebuilt it.
Over the full length of the production line, the majority of the steel structures were dismantled and then reassembled and installed at a new location. All the high-tech tools were also moved and reinstalled. All the electrical systems, air conditioning, safety systems and computer control systems were adapted to the new situation.
The floor chain lane systems were changed, as were the drives. In addition to the production line, the associated storage warehouse was also completely revamped. Various hoisting facilities, racks and conveyor belts were reinstalled. In less than 4 weeks’ time, all items and tools were moved and the production line was set up more efficiently. After a number of extensive and successful test runs, production was able to start up again.
DDM managed to optimise the complete production line for the truck cab within the planned schedule. Thanks to the change, which was done for the client’s European Optimization Program, more trucks are being produced now than ever before: production increased by over 14%.
DISMANTLING
Location
Ghent, Belgium
Deployment
- - 25 assembly and dismantling specialists
- - A large number of mobile elevated work platforms
- - Forklift trucks
- - Hoisting equipment
Size
Project duration
10 weeks
DISMANTLING
ENGINEERING
INSTALLING
CONSTRUCTING
Safety First! Always.
PROJECT LOCATION
demontage Projects
-
Dismantling of O2 degassers
Limburg, Netherlands
-
Complex asbestos project
Limburg, Netherlands
-
PVC and VCM plant
Terengganu, Malaysia
-
Demolition of production lines
Belgium
-
disassemble presses
Limburg, Netherlands
-
Dismantling 11G/12G trams GVB
Utrecht, Nederland
-
Dismantling a factory
Overijssel, Nederland
Baden-Württemberg, Duitsland
-
Dismantling lighting poles
Vlaams Gewest, België
-
Dismantling plant
Opper-Oostenrijk, Oostenrijk
-
Dismantling of paraformaldehyde plant
Flanders, Belgium
-
Dismantling of Pipework
South Holland, Netherlands
-
Dismantling production lines
Limburg, Netherlands
-
Truck cab production line
Vlaanderen, België
-
Replacing rotating dryers
Zuid-Holland, Nederland
-
Compounding unit
Pahang, Maleisië
-
Power plant in Amsterdam
Noord-Holland, Nederland
-
Removal of floating tank roof
North Rhine-Westphalia, Germany
-
Removal of water tanks
Utrecht, Netherlands
-
Turn around, shutdown in Greece
Athens, Greece
-
Turnaround Greece
Eleusis, Greece